§ 47-80. Alternative fire protection impact fee.  


Latest version.
  • (a)

    In the event an applicant believes that the impact to the fire protection system caused by fire protection impact construction is less than the impact established under the applicable fire protection impact fee land use category specified in section 47-79 such applicant may, prior to issuance of a building permit for such fire protection impact construction, file an alternative fire protection impact fee study with the county coordinator. The county coordinator shall review the alternative calculations and make a determination within 60 days of submittal as to whether such calculations comply with the requirements of this section.

    (b)

    For purposes of any alternative fire protection impact fee calculation, the fire protection impact construction shall be presumed to have the maximum impact on the county fire protection system for the appropriate fire protection impact fee land use category.

    (c)

    The alternative fire protection impact fee calculation shall be based on data, information or assumptions contained in this article and the fire protection impact fee study, or independent sources, provided that:

    (1)

    The independent source is a generally accepted standard source of planning information and cost impact analysis performed pursuant to a generally accepted methodology of planning and cost impact analysis which is consistent with the fire protection impact fee study; or

    (2)

    The independent source is a local study supported by a database adequate for the conclusions contained in such study performed pursuant to a generally accepted methodology of planning and cost impact analysis which is consistent with the fire protection impact fee study.

    (d)

    If the county coordinator determines that the data, information and assumptions utilized by the applicant comply with the requirements of this section and that the calculation of the alternative fire protection impact fee was by a generally accepted methodology, then the alternative fire protection impact fee shall be paid in lieu of the fees adopted in section 47-79.

    (e)

    If the county coordinator determines that the data, information and assumptions utilized by the applicant to compute an alternative fire protection impact fee do not comply with the requirements of this section, then the county coordinator shall provide to the applicant by certified mail, return receipt requested, written notification of the rejection and the reasons therefor.

(Ord. No. 2016-01 , Art. 13, 2-16-2016)